Brooksby Spinney
Updated: 13 January 2024
Location: Melton Road, Brooksby, LE14 2LJ
Developer: Bloor Homes
Number of units: 70 houses
Aim(s) of Project: Trial of Air Source Heat Pumps
Construction method: Masonry
Energy Compliance method: SAP 2012
Overheating compliance method: Pre-2021 Part O - standard overheating assessment
Construction start: January 2022
Construction finish: --
Bloor Homes initially intended to use Calor Gas with communal storage tanks, as this had worked on a previous site. However, the Highways Authority/ Leicestershire County Council, would not allow Calor pipes beneath adoptable roads.
As a business it is their default position to put the roads forward for adoption and therefore the option of a private road was not acceptable. Oil heating was rejected as the tanks would be very prominent in the gardens of all the properties.
Therefore, with an eye on the Future Homes Standard (FHS), they decided to look at Air Source Heat Pumps (ASHPs). The developer selected an ASHP where the flow temperature they offered for the central heating water was closer to a gas fired system.
The primary concern was to make sure that the homes were sufficiently warm.